While local government usually gives owner builders two years to complete a build, my projected date for getting the build to the final approval stage was March-April 2013, which allowed 15-16 months. However, final approval does not mean the work is over because certification does not require all the finishing touches. For example, we have yet to lay our bamboo floor boards and put in all the skirting boards, build the pantry shelves and walk in robe fittings, put up the last of the kitchen cupboards and finish painting the exterior of the house.
Some of the work we've been doing since the new year...
Paul finished off the re-engineering of four recycled casements into bifold windows for the kitchen, a job he and Nick had started some time last year...
Nick turned some of my father's prized Mackay red cedar into a balustrade rail in my studio .... and is currently turning the rest of Dad's cedar into a desk for me - that is exciting!
A group effort (Paul, Nick and I) saw the installation of the upper deck balustrades with some timber treatment still to happen ...
The battens are treated cedar and the top rail is made from beautiful old hardwood we found in a demolition yard, which I've yet to treat.
Another major achievement - the external awnings that were not on my original design but stipulated by the energy assessor. Awnings were required on the two sets of openings on the eastern side of the double storey wall and the western window of the upper storey. I'm very happy with my design, translated by Nick into a material reality, which Paul and Nick then installed. We continued the upper eastern awning around the front of the building purely for aesthetics.
And the last major task required before the final inspection....the balustrades for the internal staircase. After a good deal of talk, design, fixing, more design and more fixing, this is what Paul, Nick and I came up with....I like watching visitors' differing reactions.
While Nick and Paul were working on the inside, I started applying the exterior top coats of paint. It's not progressing at a fast pace but I'm getting it done bit by bit. The most time consuming part is painting the projecting roof battens although the final coat on all the windows will be equally tedious. The walls are the easy part. The dark colour is Bronze Fig while the rest of the walls will have half strength White Duck. The latter is a kind of greenish-white which you can still see against the white undercoat at the right and in the little upper section below (yet to be finished).
I expect there will be a few more posts yet to keep you up to date on how we continue to make this dream happen.












































